IBM C1000-132 certification exam is intended for IT professionals who have experience with IBM Maximo Manage v8.0 software and are looking to validate their expertise in the implementation of this software. C1000-132 exam tests candidates on their ability to install and configure IBM Maximo Manage v8.0 software, as well as their ability to customize and extend the software to meet the specific needs of an organization.
NEW QUESTION # 10
When creating a new Inspection form, a client requires a Work Order to be created if certain responses are recorded. Which two actions are required for this to be achieved?
- A. In the Question Options, set the Require action flag.
- B. Make the question response interactive.
- C. In Form Settings add an Action Script.
- D. Create an escalation on the QRESPONSE Object.
- E. Choose Work Order on question action.
Answer: A,E
Explanation:
According to the IBM documentation, you can create inspection forms that detail the questions and types of responses that you want to collect. The inspection forms that you create are then available to inspectors in the Conduct an Inspection tool. You can also add conditions to the response fields of existing questions on inspection forms to gather more information. You can determine which additional response fields appear to inspectors, depending on the answers they gave to inspection form questions.
To create a work order based on certain responses, you need to do two things:
Choose Work Order on question action: This option allows you to specify an action that is triggered when a certain response is selected by the inspector. For example, if a question asks "Is there any damage?", and the inspector selects "Yes", you can choose Work Order as the action that is triggered by this response. This will create a work order for repairing the damage.
In the Question Options, set the Require action flag: This option allows you to indicate that an action is required for a question. For example, if a question asks "Is there any damage?", and you set the Require action flag to Yes, then the inspector must select a response that triggers an action, such as Work Order or Notification. If they select a response that does not trigger an action, such as "No" or "N/A", they will see an error message and will not be able to submit the inspection form.
NEW QUESTION # 11
What are two of the filters in the Select Value of a Location or Asset in the Service Requests application?
- A. Service Address
- B. Public
- C. User/Custodians
- D. Work Zones
- E. Service Group/Services
Answer: A,E
Explanation:
Two of the filters in the Select Value of a Location or Asset in the Service Requests application in IBM Maximo Manage are Service Address and Service Group/Services.
NEW QUESTION # 12
How is the Lock Out / Tag Outs application structured?
- A. Define the isolation procedures on a set of related assets and specify a sequence.
- B. Specify a Lock Out on the Location or Asset and define the Tag Out Operations.
- C. Specify a Lock Out on an Asset with a Locking Device and define the Tag Out Operations.
- D. Specify a Tag Out on the Location or Asset and define the Lock Out Operations.
Answer: B
Explanation:
In IBM Maximo Manage v8.0 implementation, the Lock Out / Tag Out application is structured such that you specify a Lock Out on the Location or Asset and define the Tag Out operations. This application is used to manage the procedures and controls put in place to protect personnel from injury due to unintended or inadvertent equipment or system operation.
NEW QUESTION # 13
In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?
- A. the PM target finish date
- B. the Job Plan start date + the Job Plan duration
- C. the Job Plan finish date
- D. the Work Order target start date + the Job Plan duration
Answer: D
Explanation:
In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.
NEW QUESTION # 14
In the Budget Monitoring application, where are the budget amounts entered?
- A. Budget Record
- B. Focal Point
- C. Budget Line
- D. Budget Rules
Answer: C
Explanation:
the budget amounts in the Budget Monitoring application are entered at the Budget Line level. A Budget Line represents a specific account or category within a budget and allows for detailed tracking and analysis of budget data.
NEW QUESTION # 15
What information can be updated in the Master PM application for an associated Preventive Maintenance record (PM)?
- A. Generate Work Orders
- B. PM Hierarchy
- C. PM Forecast
- D. Work Order Status
Answer: C
Explanation:
The PM Forecast field on the Master PM record is used to specify how many days ahead you want to forecast work orders for associated PMs2. This field can be updated in the Master PM application and affects how many work orders are generated from the associated PMs.
NEW QUESTION # 16
Apart from Standard and Average, what other three costing methods can be used in the Inventory application?
- A. FILO
- B. Weighted Average
- C. LIFO
- D. FIFO
- E. Asset
- F. LILO
Answer: B,C,D
Explanation:
Apart from Standard and Average costing methods in IBM Maximo Manage's Inventory application, three other costing methods that can be used are FIFO (First In First Out), LIFO (Last In First Out) and Weighted Average.
NEW QUESTION # 17
Which application in the IBM Maximo Application Suite can be used to perform criticality scoring?
- A. Maximo Health
- B. Maximo Prevent
- C. Maximo Supervision
- D. Maximo Manage
Answer: A
Explanation:
The Maximo Health application in the IBM Maximo Application Suite can be used to perform criticality scoring.
NEW QUESTION # 18
The loT Connector provides Maximo Manage, Maximo Health and Maximo Predict the ability to connect to which two data sources?
- A. IBM Watson loT Platform
- B. Maximo Monitor
- C. Maximo Safety
- D. Maximo Assist
- E. Maximo Spatial
Answer: A,B
Explanation:
IoT Connector provides Maximo Manage, Maximo Health and Maximo Predict the ability to connect to C. IBM Watson IoT Platform and E. Maximo Monitor data sources. The IoT Connector in the Administration Work Center can be used to configure a connection to an IoT platform such as IBM Watson IoT Platform and IBM Maximo Asset Monitor1.
NEW QUESTION # 19
When users are added to multiple security groups, the authorization privileges of the security groups combine, with the exception of security groups with which setting?
- A. Autonomous
- B. Separate
- C. Independent
- D. Discreet
Answer: C
Explanation:
When users are added to multiple security groups, the authorization privileges of the security groups combine, with the exception of security groups with the "Independent" setting. When a security group has the "Independent" setting, its authorization privileges are applied separately from any other security group that the user belongs to.
NEW QUESTION # 20
What combination of information on a Work Order is used to create a histogram in the Graphical Scheduling application?
- A. Labor and Crew Hours
- B. Craft/Skill Level Quantity and Hours
- C. Craft Quantity and Hours
- D. Crew Work Group Quantity and Hours
Answer: A
Explanation:
In the Graphical Scheduling application, a histogram can be created based on the combination of Labor and Crew Hours. This histogram provides a visual representation of the distribution of labor and crew hours across different work orders and helps in identifying areas where the workload is high or low.
NEW QUESTION # 21
What is a core application in Maximo Manage?
- A. Permit to Work
- B. Maintenance Version Control
- C. Customer Billing
- D. Graphical Scheduling
Answer: A
Explanation:
The Permit to Work application is a core application in IBM Maximo Manage v8.0. This application allows users to manage work permits, ensure compliance with safety regulations, and ensure that work is authorized before it is started. Other core applications in Maximo Manage include Work Order Tracking, Asset Management, and Inventory Management.
NEW QUESTION # 22
In the Organizations application, which action is used to create Inventory Usage documents for new reservations?
- A. Work Order Options
- B. Reservation Options
- C. Inventory Options
- D. Inventory Usage Options
Answer: B
Explanation:
In the Organizations application in IBM Maximo Manage, you should use Reservation Options to create Inventory Usage documents for new reservations.
NEW QUESTION # 23
What is the purpose of the Admin mode?
- A. change System Properties without needing to shut down the Maximo server
- B. perform Database Configuration without needing to shut down the Maximo server
- C. perform administrative functions
- D. apply changes in Application Designer
Answer: B
Explanation:
The purpose of Admin mode in IBM Maximo Manage is to allow users to perform Database Configuration without needing to shut down the Maximo server.
NEW QUESTION # 24
Select all that apply
What is the priority order for selecting a Safety Plan when a Job Plan is applied to a Work Order?
Answer:
Explanation:
1 - Use the Safety Plan associated with the Asset referenced on the Work Order.
2 - Use the Safety Plan associated with the Location referenced on the Work Order.
3 - Use the Safety Plan associated with the Asset's Rotating Item, for the Asset referenced on the Work Order.
4 - Use the Safety Plan associated with the Location's Rotating Item, for the Location referenced on the Work Order.
NEW QUESTION # 25
When creating a labor record, what must be associated with it?
- A. Person Record
- B. Crew
- C. User Record
- D. Supervisor
Answer: A
Explanation:
When you create a labor record in IBM Maximo Manage v8.0, you enable a person to report time against a work request1. Before you create a labor record, you must create a corresponding person record1. A person record is defined at the System level and when a person works across multiple organizations, they need multiple Labor records linked to the same Person record2.
NEW QUESTION # 26
What is the default status in the Quick Reporting Application?
- A. INPRG
- B. APPR
- C. ENTERED
- D. DRAFT
Answer: D
Explanation:
The default status in the Quick Reporting Application in IBM Maximo Manage is DRAFT.
NEW QUESTION # 27
In the Item Master application, with what can a Kit Item be associated?
- A. Lot item
- B. Non Rotating item
- C. Service item
- D. Condition enabled item
Answer: B
Explanation:
a Kit Item can be associated with A. Non Rotating item. When you create a kit record for an item in the Item Master application, you can define the structure of the kit using the Item Assembly Structure tab1. When adding a kit to a storeroom, if the component items do not exist in the storeroom, inventory records are created for these items1. However, you cannot create item kits that contain condition-enabled, rotating or lotted items1.
NEW QUESTION # 28
In the Meters application what are the three meter types?
- A. GAUGE
- B. CHARACTERISTIC
- C. CONSTANT
- D. CONTINUOUS
- E. CALIBRATION
- F. FEATURES
Answer: A,B,D
Explanation:
In the Meters application, the three meter types are GAUGE, CHARACTERISTIC, and CONTINUOUS. GAUGE meters measure a discrete value or range of values, such as the oil pressure in an engine. CHARACTERISTIC meters measure a specific attribute of an asset, such as the temperature of an engine. CONTINUOUS meters track usage or consumption over time, such as the number of hours an asset has been in operation.
NEW QUESTION # 29
What is a licensing method used to obtain the Maximo Asset Suite?
- A. Cloud based license
- B. Feature based license
- C. Monthly license
- D. User credits license
Answer: A
Explanation:
One licensing method used to obtain the Maximo Asset Suite is a Cloud based license.
NEW QUESTION # 30
What are three integration End Points Handlers available in Maximo Manage?
- A. WSDL
- B. FLATFILE
- C. XLS
- D. XMLFILE
- E. KAFKA
- F. EMAIL
Answer: B,D,F
Explanation:
Three integration End Points Handlers available in Maximo Manage are XMLFILE, EMAIL and FLATFILE.