NEW QUESTION 13
What master data defines the quantity structure to create a standard cost estimate? There are TWO correct answers for this Question
- A. Bill of material
D .Cost center - B. Activity type
- C. Routing
Answer: A,C
NEW QUESTION 14
When would you use a statistical key figure?
- A. To identify internal cost flows
- B. To collect actual expenses for an area of responsibility
- C. To use as a tracing factor in an assessment
- D. To distribute primary expenses in a standard cost element
Answer: D
NEW QUESTION 15
You have created an asset master data record. Which other master data record can be created synchronously?
- A. Cost center
- B. Functional location
- C. Primary cost element
- D. Equipment
Answer: D
NEW QUESTION 16
What master data defines the quantity structure to create a standard cost estimate? There are TWO correct answers for this Question
- A. Activity type
- B. Bill of material
- C. Routing
Answer: B,C
Explanation:
D .Cost center
NEW QUESTION 17
What document, when saved, creates a commitment for an internal order?
- A. Sales order
- B. Accounting document
- C. Material document
- D. Purchase order
Answer: D
NEW QUESTION 18
What is included in the structure of a maintenance order?
- A. Bill of Material
- B. plan costs
- C. Construction type
- D. Activity
Answer: B
NEW QUESTION 19
How do you use the result of a released standard cost estimate? There are THREE correct answers for this Question
- A. To calculate the price of an activity type
- B. To determine a material sales price in Sales and Distribution
- C. To update the current standard price in the material master record
- D. To determine the base costs used to calculate overhead
- E. To calculate the plan costs in a production order
Answer: A,C,E
NEW QUESTION 20
Which of the following organizational levels are defined in SAP S/4HANA Finance? There are TWO correct answers for this Question
- A. Payroll area
- B. Segment
- C. Company code
- D. Controlling area
Answer: B,C
NEW QUESTION 21
Which maintenance order element includes the field values for work center, control key, and activity type?
- A. Order header
- B. Assembly
- C. Actual cost
- D. Operation
Answer: D
NEW QUESTION 22
Which processes can be automatically performed when you post an order confirmation for a production order? There are THREE correct answers for this Question
- A. Post actual costs
- B. Order settlement
- C. Goods receipt
- D. Variance calculation
- E. Goods issue
Answer: B,C,D
NEW QUESTION 23
What tasks are performed for legal reporting? There are TWO correct answers for this Question
- A. Calculate production variances
- B. Create a balance sheet
- C. Perform inventory valuation
- D. Track company car costs
Answer: B,C
NEW QUESTION 24
Which of the following sequences of purchase-to-pay process steps is valid?
- A. Source of supply determination .Vendor selection , Determination of requirements Purchase order handling .Goods receipt
- B. Determination of requirements .Vendor selection , Purchase order handling .Goods receipt .Invoice verification
- C. Vendor selection .Source of supply determination , Purchase order monitoring .Goods receipt .Handling of payments
- D. Determination of requirements .Purchase order handling . Handling of payments .Goods receipt .Invoice verification
Answer: B
NEW QUESTION 25
Which of the following can be included in a customer pricing condition record? There are TWO correct answers for this Question
- A. Surcharges
- B. Invoice amounts
- C. Discounts
- D. Order values
Answer: A,C
NEW QUESTION 26
In a project, what is linked via relationships?
- A. Networks
- B. Project definitions
- C. Activities
- D. Work breakdown structure elements
Answer: C
NEW QUESTION 27
What can you record during overall completion confirmation of a maintenance order?
- A. Measurements
- B. Planned time
- C. Notification completion
- D. Serial numbers
Answer: C
NEW QUESTION 28
How can you post internal labor costs to a network activity? There are TWO correct answers for this Question
- A. Confirmation
- B. Service entry sheet
- C. Activity allocation
- D. Distribution
Answer: A,C
NEW QUESTION 29
Which objects can you settle?
There are Three correct answers for this Question
- A. Cost center
- B. Work breakdown structure (WBS) element
- C. Maintenance order
- D. Profitability segment
Answer: B,C
NEW QUESTION 30
What is the result of posting a vendor's invoice?
- A. The PO history is updated
- B. The material document is generated
- C. The vendor's account is cleared of open items
- D. The purchase requisition is updated
Answer: A
NEW QUESTION 31
How do you view all records created for an employee? Organizational assignment
- A. Personnel action
- B. Basic personal data
- C. Personnel file
Answer: A
NEW QUESTION 32
Which documents are created when you post a valuated goods receipt for consumable materials? There are TWO correct answers for this Question
- A. Accounting document
- B. Vendor invoice document
- C. Sales order document
- D. Controlling document
Answer: A,D
NEW QUESTION 33
......
Passing Key To Getting C-TS410-1909 Certified Exam Engine PDF: https://dumpstorrent.dumpsfree.com/C-TS410-1909-valid-exam.html